Tyler ISD 2004 Bond
Board Update
February 16, 2006
· A & E Consultants
A. Barham Architects and EHRC Architects are providing Construction Administration services throughout the project duration.
B. Barham Architects and EHRC Architects are reviewing shop drawings, submittals, and RFI’s throughout the construction process.
C. Fitzpatrick Butler/PBK, Architects (FB/PBK) continues to work on the designs approved by the Board on February 2, 2006.
D. FB/PBK, TSC and Administration met with RPR and WRL on February 10th to discuss pre-construction issues and to begin budget studies based on the preliminary designs approved by the Board.
· Construction Projects
A. Bell Elementary School – New Construction
a. Work Completed
Structural steel installation is complete.
b. Work in Progress
Miscellaneous steel continues. Denson is concentrating in Area A
(2 story classroom) with drywall framing, electrical and plumbing rough-in, ductwork, fire sprinkler system and roofing. In addition, brickwork is being installed on the west wall of the two story classroom wing. Plaster work is underway as well as preparations for the metal roofing. Hanging of sheetrock commenced this week. Joe Denson of Denson Construction has assured TISD and The Staubach Company that Bell will open on time. The unknown factor in completing the project is how weather will affect progress.
c. 3-Week Look Ahead
Work items listed above will continue in Area A and commence in Area B. RTU ‘s to be delivered the week of Feb 20th.
d. Progress Photos
B. Ramey Elementary School – New Construction
Structural steel installation is approximately 85% complete.
Structural steel installation continues in Area D. Drywall framing and rough-in for plumbing, ductwork, electrical, fire sprinkler continue. Masonry crews are working in the Gym/Cafetorium and the east wall of the two story wing. Roofing work continues in Areas A, B and C. Joe Denson of Denson Construction has assured TISD and The Staubach Company that Ramey will open on time. The unknown factor in completing the project is how weather will affect progress.
c. 3-Week Look Ahead
Masonry work will continue at the Gym/Kitchen/Cafetorium and brickwork at the east wall of the two story wing.
Structural steel will continue as well as drywall, plumbing and electrical rough-in, fire sprinkler system and ductwork.
d. Progress photos
C. Dr Bryan C Jack Elementary – New Construction
a. Work Completed
Approximately 65% of the second floor slab has been poured.
b. Work in Progress
Miscellaneous steel is being placed in Area 1 (two story wing). The two story wing is being built from east to west. Drywall framing and rough-in for electrical, plumbing and ductwork is underway. Concrete paving and sidewalks are approximately 80% complete.
c. 3-Week Look Ahead
Structural steel installation will continue. Drywall, rough-in for plumbing, ductwork, electrical and fire sprinkler will continue.
d. Progress Photos