Tyler ISD 2004 Bond
Board Update
August 17, 2006
· A & E Consultants
A. Barham Architects are providing Construction Administration services throughout the project duration for Bell/Ramey.
B. EHRC Architects are providing Construction Administration services throughout the project duration for Jack/Douglas.
C. Fitzpatrick Butler/PBK, Architects (FB/PBK) are providing Construction Administration services throughout the project duration for Austin/Bonner.
· Construction Projects
A. Bell Elementary School – New Construction
a. Work Completed
Substantial Completion was established as of August 11, 2006.
b. Work in Progress
Denson is working on the “Punch List” which is the correction of deficiencies.
c. 3-Week Look Ahead
Complete Punch List by September 11th.
d. Progress Photos
B. Ramey Elementary School – New Construction
Substantial Completion was established as of August 11, 2006.
Denson is working on the “Punch List” which is the correction of deficiencies.
c. 3-Week Look Ahead
Complete “Punch List” by September 11th
d. Progress photos
C. Dr Bryan C Jack Elementary – New Construction
a. Work Completed
All structural steel is complete.
b. Work in Progress
Finish work continues at the first and second floor of east and west ends of building. Drywall framing and rough-in for electrical, plumbing, fire sprinkler and ductwork is underway on the one story classroom wing. Technology cable installation continues. Masonry work continues at the Gym/Cafetorium and brickwork at the two story classroom wing. Metal roofing will continue.
c. 3-Week Look Ahead
Work item listed above will continue.
d. Progress Photos
D. Douglas Elementary School-New Construction
a. Work Completed
Approximately 10,000 square feet of slab is poured and a 25,000 square foot pour was made on the 11th. All footings for the foundation are complete.
b. Work in Progress
Plumbing and electrical underground continue at the kitchen. Structural steel commenced August the 9th.
c. 3-Week Look Ahead
Foundation and underground work for plumbing and electrical will continue at the kitchen. The structural steel work for the south end of the two story classroom wing continues.
d. Progress Photos
E. Austin Elementary School
a. Work Completed
The building pad dirtwork is complete.
b. Work in Progress
Dirtwork continues at the parking lots. The concrete foundation sub has mobilized and will commenced work on August 14th. The retaining wall subcontractor mobilized and started the week of August 14th.
c. 3-Week Look Ahead
Retaining wall and foundation subcontractors will continue as described above. The plumbing and electrical underground will commence the week of August 28st.
d. Progress Photos
F. Bonner Elementary School
a. Work Completed
The building pad dirtwork is complete.
b. Work in Progress
The concrete foundation sub has mobilized and will commenced work on August 14th. Retaining wall subcontractor continues to work on the west side of the site and started work on the south side of site August 14th.
c. 3-Week Look Ahead
Retaining wall and foundation subcontractors will continue as described above. The plumbing and electrical underground will commence the week of August 21st.
d. Progress Photos
END