Tyler ISD 2004 Bond
Board Update
April 20, 2006
· A & E Consultants
A. Barham Architects and EHRC Architects are providing Construction Administration services throughout the project duration.
B. Barham Architects and EHRC Architects are reviewing shop drawings, submittals, and RFI’s throughout the construction process.
C. Fitzpatrick Butler/PBK, Architects (FB/PBK) continue to work on the designs for Austin and Bonner. April the 17th, Administration and Staubach reviewed 75% complete drawings on the two projects.
D. Eubanks Harris Roberts Craig Architects completed the construction documents for Douglas Elementary School.
· Construction Projects
A. Bell Elementary School – New Construction
a. Work Completed
Drywall framing, ductwork, plumbing, fire protection piping and electrical rough-in are complete.
b. Work in Progress
Denson is concentrating in Area A (2 story wing) with the finish trades such as painting, ceramic tile, ceiling grid and hanging light fixtures. Also Denson is working in areas B, C and D with the hanging of sheetrock, electrical wiring and plumbing pipe insulation, ductwork insulation. In addition, brickwork continues and concrete is being poured in the courtyard. Technology cabling continues. The unknown factor in completing the project is how weather will affect progress.
c. 3-Week Look Ahead
Work items listed above will continue in Area A, B, C and D.
Permanent power should be turned on approximately April 21st.
d. Progress Photos
B. Ramey Elementary School – New Construction
Drywall framing, ductwork, plumbing, fire protection piping and electrical rough-in are complete.
Denson is concentrating in Area A (2 story wing) with the finish trades such as painting, ceramic tile, ceiling grid and hanging light fixtures. Also Denson is working in areas B, C and D with the hanging of sheetrock, electrical wiring and plumbing pipe insulation, ductwork insulation. In addition, brickwork continues and concrete is being poured in the courtyard. Technology cabling continues. The unknown factor in completing the project is how weather will affect progress.
c. 3-Week Look Ahead
Work items listed above will continue in Area A, B, C and D.
Permanent power should be turned on approximately April 28st.
d. Progress photos
C. Dr Bryan C Jack Elementary – New Construction
a. Work Completed
The second floor slab has been poured.
b. Work in Progress
Structural steel erection continues in the one story classroom wing and the Gym/Cafetorium. Drywall framing and rough-in for electrical, plumbing, fire sprinkler and ductwork is underway. Sheetrock is being installed on the first floor, technology cable tray installation continues. Masonry work continues at the Gym/Cafetorium and brickwork at the two story classroom wing. Built-up and metal roofing will continue.
c. 3-Week Look Ahead
Structural steel installation will continue. Drywall, rough-in for plumbing, ductwork, electrical and fire sprinkler will continue.
d. Progress Photos
D. Douglas Elementary School-New Construction
a. Denson Construction is bidding the project on May 4th.