Tyler ISD

2004 Bond Board Update

July 26, 2005

 

 

·        A & E Consultants

 

A.     Both Design Teams will be presenting final color boards to each campus in September.

 

B.     Both design teams are providing Construction Administration services throughout the project duration.  

 

·        Construction Projects

 

A.                 Henry M. Bell Elementary School – Gym Relocation

 

a.       Work Completed 

Metal building is erected, electrical and HVAC is complete.  Approximately 50% of gym equipment has been reinstalled.

 

b.      Work in Progress

Painting of the floor.  Gym equipment installation.  Completion of punch list.

 

c.       3-Week Look Ahead

Project will be complete by August 5th.

 

d.      Progress Photos

 

B.                 Henry M. Bell Elementary School – New Construction

 

a.       Work Completed 

Earthwork is 95% complete.   

 

b.      Work in Progress

Storm drainage from 5th street to school site will be complete July 25th.  Concrete submittals have been submitted to the architect.

 

c.       3-Week Look Ahead

Storm drain next to building will commence next week.  Water and sanitary sewer outside the building line will commence in two weeks. 

 

d.      Progress Photos 

 

C.                 Ramey Elementary School

 

a.       Work Completed

       Earthwork is 50% complete.

 

b.      Work in Progress

Remaining earthwork in progress.

 

c.       3-Week Look Ahead

Earthwork will continue.  Relocate existing 18” water main.  Utility work will continue.

 

d.      Progress Photos

 

D.                 Rice/Owens Relief Campus – awaiting Department of Justice approval to begin civil package.