Tyler ISD 2004 Bond
Board Update
July 19, 2007
· A & E Consultants
A. EHRC Architects are providing Construction Administration
services throughout the project duration for Douglas/Peete.
B. Fitzpatrick Butler/PBK, Architects (FB/PBK) are providing Construction Administration services throughout the project duration for Austin/Bonner.
· Construction Projects
A. Douglas Elementary School-New Construction
a. Work Completed
General construction is complete on the building.
Punch out is approximately 70% complete.
b. Work in Progress
Punch out of the building continues. The exterior work, including
paving, courtyard, irrigation, landscaping, fencing and related items
will continue.
c. 3-Week Look Ahead
Punch out should complete by August 5th.
The exterior work will complete sometime in August. Every effort is being made to complete the contract before the ribbon cutting.
d. Comments
Douglas building portion of the contract completed approximately one week behind schedule, primarily because of one subcontractor and the weather. The exterior work is approximately six weeks behind schedule because of the weather.
C. Austin Elementary School-New Construction
a. Work Completed
General construction is complete on the building.
Punch out is approximately 75% complete.
b. Work in Progress
Punch out of the building continues. The exterior work, including
paving, courtyard, irrigation, landscaping, fencing and related items
will continue.
c. 3-Week Look Ahead
Punch out should complete by August 5th.
The exterior work will complete sometime in August. Every effort is being made to complete the contract before the ribbon cutting.
d. Comments
Austin building portion of the contract completed approximately one week late because of one subcontractor. The exterior work is approximately five weeks behind schedule because of the weather.
D. Bonner Elementary School-New School
a. Work Completed
General construction is complete on the building.
Punch out is approximately 90% complete.
b. Work in Progress
Punch out of the building continues. The exterior work, including
paving, courtyard, irrigation, landscaping, fencing and related items
will continue.
c. 3-Week Look Ahead
Punch out should complete by July 31st.
The exterior work will complete sometime in August. Every effort is being made to complete the contract before the ribbon cutting.
d. Comments
Bonner building portion of the contract completed on time. The exterior work is approximately five weeks behind schedule because of the weather.
E. Peete Elementary School-New School
a. Work Completed
Structural steel erection is 95% complete. Drywall framing is 85% complete. Brick work is approximately 60% complete.
b. Work In Progress
Drywall framing, exterior sheathing and sheetrock will continue.
Rough-in of electrical, plumbing, fire sprinkler system and ductwork
will continue. Technology cable tray and HVAC controls wiring continues. Exterior elements such as brickwork, built-up roofing, metal roofing and plaster framing are underway. Window installation continues.
c. 3-Week Look Ahead
The items listed above will continue as well as concrete sidewalks and paving.
e. Comments
Peete building is approximately one week behind schedule and the site work is approximately three weeks behind schedule. With clear weather, the site work will be back on schedule in approximately 30 days.
The seven schools, as a whole, are under budget for the 2004 Bond Program.