Tyler ISD 2004 Bond

Board Update

June 18, 2007

 

 

·        A & E Consultants

 

A.                            EHRC Architects are providing Construction Administration

                  services throughout the project duration for Douglas/Peete.

 

B.                             Fitzpatrick Butler/PBK, Architects (FB/PBK) are providing Construction Administration services throughout the project duration    for Austin/Bonner.

 

·        Construction Projects

 

            A.        Douglas Elementary School-New Construction

 

a.   Work Completed                                         

General construction is complete on the building.

 

b.  Work in Progress

       Punch out of the building is underway.  The exterior work, including

                                           paving, courtyard, irrigation, landscaping, fencing and related items

                                           will continue.

 

c.       3-Week Look Ahead

Work items mentioned above will continue

 

d.      Comments

Douglas is on schedule.

 

 

C.      Austin Elementary School-New Construction

 

a.   Work Completed 

      General construction is complete on the building.

 

b.      Work in Progress

Punch out of the building is underway.  The exterior work, including

                                           paving, courtyard, irrigation, landscaping, fencing and related items

                                           will continue.

 

c.       3-Week Look Ahead

The work items listed above will continue. 

 

d.      Comments

RPR is on schedule except for the electrical which is approximately

                  one week behind.

 

D.      Bonner Elementary School-New School

 

a.       Work Completed

       General construction is complete on the building. 

     

b.   Work in Progress

Punch out of the building is underway.  The exterior work, including

                                           paving, courtyard, irrigation, landscaping, fencing and related items

                                           will continue.

 

c.   3-Week Look Ahead

Work items listed above will continue. 

 

d. .Comments

Bonner is on schedule. 

 

E.                  Peete Elementary School-New School

 

   a.   Work Completed

Structural steel erection is 90% complete. Drywall framing is 75% complete.

 

b.   Work In Progress

       Drywall framing, exterior sheathing and sheetrock will continue.

       Rough-in of electrical, plumbing, fire sprinkler system and ductwork

       will continue.  Technology cable tray and HVAC controls wiring has 

commenced.  Exterior elements such as brickwork, builtup roofing, metal roofing and plaster framing are underway.

 

           c.    3-Week Look Ahead

The items listed above will continue as well as window installation.

 

e.       Comments

Peete is on schedule.

 

                         The seven schools, as a whole, are under budget for the 2004 Bond Program.

                                                                       

 

 

                    END