Tyler ISD 2004 Bond
Board Update
June 18, 2007
· A & E Consultants
A. EHRC Architects are providing Construction Administration
services throughout the project duration for Douglas/Peete.
B. Fitzpatrick Butler/PBK, Architects (FB/PBK) are providing Construction Administration services throughout the project duration for Austin/Bonner.
· Construction Projects
A. Douglas Elementary School-New Construction
a. Work Completed
General construction is complete on the building.
b. Work in Progress
Punch out of the building is underway. The exterior work, including
paving, courtyard, irrigation, landscaping, fencing and related items
will continue.
c. 3-Week Look Ahead
Work items mentioned above will continue
d. Comments
Douglas is on schedule.
C. Austin Elementary School-New Construction
a. Work Completed
General construction is complete on the building.
b. Work in Progress
Punch out of the building is underway. The exterior work, including
paving, courtyard, irrigation, landscaping, fencing and related items
will continue.
c. 3-Week Look Ahead
The work items listed above will continue.
d. Comments
RPR is on schedule except for the electrical which is approximately
one week behind.
D. Bonner Elementary School-New School
a. Work Completed
General construction is complete on the building.
b. Work in Progress
Punch out of the building is underway. The exterior work, including
paving, courtyard, irrigation, landscaping, fencing and related items
will continue.
c. 3-Week Look Ahead
Work items listed above will continue.
d. .Comments
Bonner is on schedule.
E. Peete Elementary School-New School
a. Work Completed
Structural steel erection is 90% complete. Drywall framing is 75% complete.
b. Work In Progress
Drywall framing, exterior sheathing and sheetrock will continue.
Rough-in of electrical, plumbing, fire sprinkler system and ductwork
will continue. Technology cable tray and HVAC controls wiring has
commenced. Exterior elements such as brickwork, builtup roofing, metal roofing and plaster framing are underway.
c. 3-Week Look Ahead
The items listed above will continue as well as window installation.
e. Comments
Peete is on schedule.
The seven schools, as a whole, are under budget for the 2004 Bond Program.
END