Tyler ISD 2004 Bond

Board Update

December 14, 2006

 

 

·        A & E Consultants

 

A.     EHRC Architects are providing Construction Administration services throughout the project duration for Jack/Douglas.

 

B.     Fitzpatrick Butler/PBK, Architects (FB/PBK) are providing Construction Administration services throughout the project duration for Austin/Bonner.

 

·        Construction Projects

 

 

A.                 Dr Bryan C Jack Elementary – New Construction

                                

a.       Work Completed

All work is complete except the fence at the colonnade.

 

                                    b.  Work in Progress

Punch list work continues

 

c.       3-Week Look Ahead

Work items listed above will continue.

 

d.      Comments

The project is scheduled to be complete in January 2007.

Construction Manager is working on punch list.

Bryan C Jack is under budget.

 

                       

 

 

 

            B.         Douglas Elementary School-New Construction

 

a.   Work Completed                                         

All structural steel erection is complete (exclude colonnade).

 

b.  Work in Progress

Miscellaneous steel erection continues on the 1 story wing and the gym/cafetorium.  Drywall framing on the exterior of the 1 story classroom wing continues and brick work is approximately 40% complete.  Interior drywall framing and sheetrock work is underway in the 1 and 2 story classroom wing.  HVAC ductwork, plumbing and electrical rough-in continues as well as the fire sprinkler piping and technology cable tray.  Ceramic tile at the toilets are in progress at the 2 story wing, as well as tape, bed and texturing of the sheetrock walls.

                                           

c.       3-Week Look Ahead

Work items mentioned above will continue.

 

d.      Comments

Douglas is ahead of schedule, at this point, and under budget.

 

C.      Austin Elementary School-New Construction

 

a.   Work Completed 

All slab on grade work is complete. Retaining wall work is complete as well as the CMU work.  The 2nd floor slab was placed on November 10th.

 

b.      Work in Progress

Structural steel erection is approximately 90% complete.  The brick work continues on the north side of the building. Drywall framing is underway at Administration area, 2 story classroom, Mainstreet, and Cafetorium areas. In addition, wall and above ceiling rough-in for plumbing, electrical, ductwork for HVAC and fire protection.

 

c.       3-Week Look Ahead

 The work items listed above will continue.

 

d.      Comments

RPR is on schedule and on budget.

 

 

 

 

 

 

D.      Bonner Elementary School-New School

 

a.   Work Completed 

All slab on grade work is complete.  Retaining wall is complete. 

CMU work at the gym is complete.

 

b.   Work in Progress

Structural steel erection is approximately 70% complete.  In addition, wall and above ceiling rough-in for plumbing, electrical, ductwork for HVAC and fire protection.

Drywall framing is underway at the 2 story classroom area and the Cafetorium.

 

c.   3-Week Look Ahead

Work items listed above will continue. 

 

d.  .Comments

Bonner is on schedule and on budget.

 

 

E.                  Peete Elementary School-New School

 

   a.   Work Completed

 

b.    Work In Progress

                                            Denson Construction mobilized Dec 4th and clearing commenced.

 

            c.    3-Week Look Ahead

                   Site clearing of trees will continue and dirt work will commence.    

                 

                                    d.    Comments

                                           Project scheduled to complete November 2007.

 

 

                                                                        END